Question: 1 / 400

What is a "punch list" in construction?

A schedule for construction tasks

A list of materials needed

A document that outlines incomplete or inadequate work that must be addressed

A "punch list" in construction refers to a document that itemizes incomplete or inadequate work that needs to be resolved before a project can be considered finished. This typically arises during the final stages of a construction project, when the project manager, contractor, or client walks through the site to identify any issues that require attention. The punch list serves as a checklist for the contractor to address these items, ensuring that all aspects of the work meet the required specifications and standards before the final approval or handover is granted. This process is essential for quality control and project completion, ensuring that everything is executed to the client’s satisfaction.

In contrast, the other options refer to different aspects of the construction process—schedules and lists of materials, which do not specifically focus on identifying and addressing incomplete work, and a list of workers, which pertains more to project management rather than quality assurance.

Get further explanation with Examzify DeepDiveBeta

A list of workers on a job site

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy